just got to guesstimate cable now and add it on. Materials nearly at 2grand without lights or cable and thats at cost.Just done a 7 bedder and that was £15000 approx. to start and ended up at £320000 approx. with down lights and outside lights etc so don't underestimate the labour side of things as will take an age to do believe me
suggest 300m 2.5mm, 400m 1.0mm ( or 1.5mm ) and 100m 3 core/E. then guess the run lengths for 6mm ( or 10mm ).
As they say price materials and labour and compare with your price per point.. I'd prefer materials +20% then labour on top . It's hard I say without actually seeing it but we all guessing and working like f*** if we feel we've under estimated .. I'm sure you said you have nice smile so someone might help ya from here...

I haven't seen it either. Should have gone visit first. Job starts building next week need quote in ASAP. Have another job to price for in London. That's going to be done off drawings.
As long as I don't make a loss ill be happy.
that 7 bed mansion on the drawings looks like a proper big job. One month on the site or more. You dont wanna do it for free...
Add some moneys to employ some helping hands, pulling cables in 3 floor property on your own can be a tough business.


Im thinking I will do the separate labour and materials system, then compare it to the per point method. Reconfiguring the lighting points. Im not going to price for any light fittings. Theres LED downlights, 'decorative pendants', gable/soffit lights and external/internal wall lights. Thats all personal preference.![]()
and remember to add a fudge factor for the other things you have forgotten, but keep it reasonable.