Hope the op doesn’t take this the wrong way as I’m not intending to insult but if you are at the stage of costing jobs of this size you shouldn’t really need to much advice on here........and you should probably be aware that if a builder is supplying materials they will be ---- to say the least...:)
 
Hope the op doesn’t take this the wrong way as I’m not intending to insult but if you are at the stage of costing jobs of this size you shouldn’t really need to much advice on here........and you should probably be aware that if a builder is supplying materials they will be **** to say the least...:)
The only advantage I could see for the builder is if the OP isn’t VAT registered and being newbuild they will be zero rated....saving himself 20% on the material.
 
When I'm working out labour I break it down to small sections for example start with the simple things how long does it take you to fit a CU , how long to wire a ring , how long to chop out a back box . How long to fit a down light ETC .
 
How have you managed to secure all this work without having any idea on what you are charging?

Didn’t they ask for a price before giving you the jobs?
Hi , just to clearify that i just bought this business from one of my friend ‘s family, he had cancer and passed away 2 months ago so i took over all his business without any knowledge, and his customers are happy to continue with me but i will have to keep same standard , his team was good so i am carrying whole his team (5 electrians) , at the moment i have 4 big houses and 14 (2bedroom) flats all newbuilds , i have to sort out all labour prices on Monday and have to start work next week .. i have got the job 100% and i know builder will offer me same price as they were giving to my friend because they were dealing with him from last 20 years .. but still i want to make sure the labour prices before i confirm the deal , and i hope you guys understand now my situation..
thanks
 
real quick math
labour only make sense to calc it using day rate
say £250/day/spark

1st fix (depending on spec) 10/12days for 2 sparks
mid fix 1/2 days for 2 sparks
2nd fix (depending on spec) 2/3 days for 2 sparks

8500+vat per 6bed house -maybe add a bit on when they dont order the collect gear
 
Are there no records from previous works for these builders? Have they given you the plans? Used to do work for Barretts etc we had a "bible" with the drawings in, there could be different layouts affecting installation cost
 