T

The Ghost

If your bored or like a challenge I thought (maybe wrongly) this might be interesting to trainees and maybe others. As the title convert three way switching to two way (Sw 2 + 3) threeway.jpg
threeway.jpg
danlers time lag (Master and slave) using switch 2 and 3. Assume you cannot find the junction box. Can it be done? Note we have L in at switch 1, no accessible switch return. I included a couple of photos to give the ---- drawing some context. The switch return (green) is pure conjecture on my part, but it must be something along those lines. There is no switch return wire at any switch.

Bottom of stairs intermediate.JPG


FIrst two way in comms room picks up live from adjacent switch.JPG


Top of stairs.JPG
 
Looks like a standard 2-way to me. Feed in and feed out in the common of Sw1, strappers through intermediate switch and yellow from Sw3 is the SL to the light. If your getting rid of Sw1 you could connect the live through to sw2 and connect the SL and L through in parallel to switch 3. Or am I missing something?
 
Sorry did not label it but from the photos and diagram you should see the live comes into sw 1 common-to either L1 or L2 on red cables to the intermediate L1 and L2 (Sw 2) correspondingly (all belled out by the way) then from the intermediate top, to the three core R-Y-B two way switch (Sw 3) again belled out from intermediate L1 L2 top to L1 L2 on sw 3 hope that's clear. There is no switch return that I can make out. Or am I missing something?
 
Last edited by a moderator:
Bear in mind the junction box is assumed as there is no other way the lights can switch on which they do by the way. I have had no sight of the junction box, could be in the wall joined to old MICC (quite common in this building) or JB in loft 20 foot up with a 2 foot by 2 foot hatch leading to a sargasso sea of cables dust an inch thick and billions of data cables just thrown over the loft and so on.
 
There are two lights on the stairs. If the yellow cable is the switch return where does the common go to at switch 1 if not the yellow cable at switch 3?
sw 1 common perm live, strippers through to int, other side of int to junction box, strappers connected to sw3 and Yellow from common sw 3 is SL to lights.
 
Last edited by a moderator:
Yellow from common sw 3 is SL to lights.
Agreed, now you can't (for the sake of argument and practicalities) get to the junction box. So I want to convert this to two way master and slave time lag switch. So usually L and Sw return to master and use two of the strappers for the slave. But the L is at switch one which is being gotten rid of. The answer is a nothing to do with this problem I might add. It is just a mind bender for trainees really, and hopefully they might think it can't be done will have to do something else which I did.
 
you could do with a old timer
Nah the problem is sorted just thought I'd throw it out there for a bit of light entertainment. Lets just say it's thinking outside the box, or cutting the gordian knot. I just thought it might be good for trainees to have a think about as it's the sort of thing we come across all the time and have to think it through.
 
Well maybe not.
threeway3.jpg
Ok if I go with the idea the yellow is the sw. return which was my first thought. Where does the mystery wire go? Maybe it is another feed to another light. But anyway the thing is, is it possible to do away with the first switch and run a master/slave time lag. And by the way at the light fitting it is a red cable as the sw. return. I know this is all a bit silly as I said just a bit of fun.
 
It's late and I've had a few birthday beers tonight, but my thoughts are to run 2 masters rather than master and a slave.

Doesn't look like you have enough wires otherwise.

Does the live out (red) go to an Em light ?
 
Does the live out (red) go to an Em light
Sw 1 picks up its L from the adjacent grid switch, which is a fish key switch for the emergency lights with a separate supply to the emergency lights on the same circuit. If you switch off the fish key switch emergencies and lights on stairs go out together. Any yes it is a bit late to think this through.
 
Last edited by a moderator:
2 masters rather than master and a slave
In order to run anything you would have to have a live and switch return. If I do away with sw. 1 there will be no live at sw. 2 and sw. 3. Anyway I had hoped some trainees would seize on this and lead the way. Shame they have not. I really don't want to make everything too obvious.
 
Last edited by a moderator:
Anyway the two way switching is not the issue and is a complete red herring which I did not want to say but there I've blurted it out now as I'm getting tired. First off the whole of the two way switching would be disposed of. For a master and slave or master and master you only need two cables. Just a clue to the clueless.
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Interesting three way conversion to two way and swap for time lag.
Prefix
N/A
Forum
UK Electrical Forum
Start date
Last reply date
Replies
57
Unsolved
--

Advert

Thread statistics

Created
The Ghost,
Last reply from
MFS Electrical,
Replies
57
Views
5,539