E
ezzzekiel
Hi, need a little help on something i dont quite understand, hope you can help - here goes- if you were to do a job (any job large or small) then first step is to check main earth, main bonds are ok - so here lies the questions.......
1. if no bonding at all - no work unless its put right
2. bonding exists but its not as per 17th (ie main 6mm not 10mm) then would it require upgrading, marking down as inadequate or be ok if its continuity is good?
1. if no bonding at all - no work unless its put right
2. bonding exists but its not as per 17th (ie main 6mm not 10mm) then would it require upgrading, marking down as inadequate or be ok if its continuity is good?