Welshsparky
Sorry to sound daft but what exactly would DNO have to do ? Would it not just be a case of supplier fitting one meter per phase?
It's a three phase supply , could this not be split into 3 single phase meters ( one to supply shop and other two to supply two flats?
- - - Updated - - -
Then sub meters to which are accessible to tenants?
What I am actually trying to asking is would it be acceptable to treat these as 3 single phase supply's , have 1 meter per supply ( obviously two of them already are ) and then fit a payg meter for each flat in an accessible area for the tenants?
What I am actually trying to asking is would it be acceptable to treat these as 3 single phase supply's , have 1 meter per supply ( obviously two of them already are ) and then fit a payg meter for each flat in an accessible area for the tenants?
I would say you can, speak to DNO first, if you think about it, take a big block of flats 3phase supply not every body is with the same supplier are they.The problem you got is the meter's they have to be near cut out,without supply shift it would mean sub meter's (paygo) but then it's controlled by landlord they by the tokens and charge tenants what they like.
That's cos they use a cabinet with DNO fuses which splits the supply into multiply supplies to feed each flat.
You can have different suppliers on one service cable. Typical example....1 x 3 phase cable...3 x separate 1 phase meters.But then that leaves one supplier to supply the building. The landlord would then need to sub meter. What if one tenant wants to buy their electricity off EDF say and the other tenant from EON. That can't happen with only one supply into the building.