Hi all

Got to price for a new build bloke of 3 flats. irst time I have quoted a new build so was thinking three days first fix and two days secound fix does this sound about right?

The flats are two bedroom with three sockets in each room and centre light just basics really nothing fancy. I was thinking three weeks in total first and secound fix with two of us. Done new builds when on the books but not on my own so would be greatfull for any replys.

Thanks
 
Anything else to go in? Fire alarm? Data? Ventilation units? Supply from plant swa or concentrics??
 
No just smoke alarms tv point in bedrooms and living room, basic really nothing fancy. I was thinking one week first and second fix? Do u think that's about right.

Thanks
 
We worked as a team of two on student apartments 3beds & ensuites.& 1 kitchen.

We didn't chop boxes in as dry liners were doing them.

We 1st fixed 3 a day.......2nd fix & test took just over a day per apartment
 