Has anybody submitted ROOFIT accreditation's, Their process is extremely slow. We commissioned two systems at the end of June , paperwork was sent in to them and OFGEM want readings from 5th Sept. That is 2 months loss of generation.
I'm in the process of getting one through that was started in august and going has been slow. My understanding is that the date of application is the eligibility date though.
No, I started mine in May. Takes up to 3 months to have accreditation past. They asked for metering reading last week, my customer lost 65000 units. Has anyone else had any experience
For ROOFIT the Eligibility Date is the date OFGEM receive the application or the commissioning date, whichever is later. Their only quibble with an application could be if they considered that the paperwork was incomplete initially.
That's is what they do. We had the FIT paper work sent to NPOWER and solar commissioned on the 23rd with witness test signed.
There is no one to talk to, all done via emails
Installation was done in 4 weeks