Dizzy_Maskell

Did a PIR 3 years ago and as there was not an RCD in sight recommended they upgraded their system.
It's the third year anniversary and we are back this morning to carry out EICR and guess what RCBO module fitted to every circuit.
Doing IR tests and now can't get a global any where got to remove every cable from every RCBO and then struggle get them back in,

It's ironic really but we have caused out self an absolute gruler. It's nice to see our recommendations get done but not nice struggling with these awkward modules arghhhhhhh!!!!

Can we recommend RCBO are taken out again to save us a nightmare ???
 
why didn`t you just drop the conductors out of each RCBO but without dragging them out of the board...

then you use breakout box & lightmates etc out in the install.....get IR from there....
 
That's what I did mate but last time we remember getting global on the board for the IR tests.
 
caus if you work in pairs and have a good understanding then it shouldn`t take much longer to go about it in the way i suggested....

you cant be sure either if the IR had come down since the last time it was subjected to any testing ....can you...

so a `global` IR could have been coming back flat.....

think parrallel paths....:D
 
Flip all the neutral cables up and use jumper cables from neutral to neutral, etc and then do a global IR.
 
caus if you work in pairs and have a good understanding then it shouldn`t take much longer to go about it in the way i suggested....

you cant be sure either if the IR had come down since the last time it was subjected to any testing ....can you...

so a `global` IR could have been coming back flat.....

think parrallel paths....:D

Well turns out was all >100 in the end just took longer get there,

The thread was really to see of any one else causes themselves this issue or others by doing work?
 
Did a PIR 3 years ago and as there was not an RCD in sight recommended they upgraded their system.
It's the third year anniversary and we are back this morning to carry out EICR and guess what RCBO module fitted to every circuit.
Doing IR tests and now can't get a global any where got to remove every cable from every RCBO and then struggle get them back in,

It's ironic really but we have caused out self an absolute gruler. It's nice to see our recommendations get done but not nice struggling with these awkward modules arghhhhhhh!!!!

Can we recommend RCBO are taken out again to save us a nightmare ???

Answer: lots of probes and jump leads, and a crack team of highly trained octopuses. :-)
 
Well turns out was all >100 in the end just took longer get there,

The thread was really to see of any one else causes themselves this issue or others by doing work?
but if you`d done it global would it have been?..it may have...but then again it may not....

think parrallel paths....:D

you know you can have a min of 2 Meg on a global dont you.....but i`v had it upteen times where you do em global...flat as a fart....but all come back good when done individual.....
 
  • Like
Reactions: 1 person
Oh many a time pal, that's the fun of it though or usually the last circuit in the board is down and then the huge 24 way TP board goes clear
 
  • Like
Reactions: 1 person

Similar threads

D
Replies
3
Views
924
D

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Self inflicted pain in the ar#e
Prefix
N/A
Forum
UK Electrical Forum
Start date
Last reply date
Replies
10

Advert

Thread statistics

Created
Dizzy_Maskell,
Last reply from
Dizzy_Maskell,
Replies
10
Views
1,251

Advert