IMO DVDs have no place in a site induction - they should be for site specific stuff like site security, welfare facilities, location of muster point etc. Anything generic enough to warrant producing a DVD can be done any time, anywhere, such as when you do your ECS/CSCS test. Not much point having a card if at every site you get told to go outside if there's a fire and tell a grown-up if there's something you're unsure of.
 
Mate of mine was a private building inspector and had been in the trade for 40+ years. He went on a site and the site manager insisted on giving him a full 40 minute induction. As he walked out of the site office he noticed a JCB digger being used as a crane. He went back in and reported a H&S breech to the site manager as well as people working under the JCB load without hard hats. Later he noticed scaffolding being overloaded with heavy blocks, when he got back to the office he reported this as well knowing that each breech was at least 20 minutes work for the site manager.

The next site the site manager said to him "you look as if you have been around a bit, do you want the full induction or just the site specific issues?" My mate took the site specific issues and was out in 10 minutes knowing exactly what the main risks on the site were and the site manager could get on with his job.

The obsession with H&S is way over the top and in my view makes things more dangerous because it gets treated as a joke. Another mate had to put on a fall harness with something like a 15 ft drop, he was working 12ft off the floor, the H&S manager thought this was OK as he was seen to wearing the correct gear even though it was worthless and getting in his way.

I am glad I started working for myself before all the jobsworth H&S inspectors started.
 
I remember coming onto a site and being told how important the induction was, posters all over the place, cards to sign, and carry, registers to complete.

"Just watch this video, yeah sorry the sound isn't working but you will probably pick it up"!
 
Mate of mine was a private building inspector and had been in the trade for 40+ years. He went on a site and the site manager insisted on giving him a full 40 minute induction. As he walked out of the site office he noticed a JCB digger being used as a crane. He went back in and reported a H&S breech to the site manager as well as people working under the JCB load without hard hats. Later he noticed scaffolding being overloaded with heavy blocks, when he got back to the office he reported this as well knowing that each breech was at least 20 minutes work for the site manager.

The next site the site manager said to him "you look as if you have been around a bit, do you want the full induction or just the site specific issues?" My mate took the site specific issues and was out in 10 minutes knowing exactly what the main risks on the site were and the site manager could get on with his job.

The obsession with H&S is way over the top and in my view makes things more dangerous because it gets treated as a joke. Another mate had to put on a fall harness with something like a 15 ft drop, he was working 12ft off the floor, the H&S manager thought this was OK as he was seen to wearing the correct gear even though it was worthless and getting in his way.

I am glad I started working for myself before all the jobsworth H&S inspectors started.


nah we don't bother with harness we have bloody good lookouts and predetermined call signs when climbing over ahu's, tray,ladder racking etc
 
only induction i ever attended that wasn't just a talk on site rules, was down the salt mine. 2 hours of instruction on how to use the breathing apparatus, follow escape routes , fire drill etc.

Where was the salt mine?
 
Under the Mersey Sausage. Well they told him it was salt anyway, one of Maggie's job creation wheezes after she was told that she couldn't just abandon Liverpool :)
 