OK, I'm guessing you're not a sparky so I'll give you a direct answer - if there's one "feed" you shouldn't have any more cables unless its a radial circuit. I definitely wouldn't be adding 2 spurs to what could already be a spur.

No I am not a sparky, it is in the garage and it is defently a spur you can see the main cable run in to the socket and the spur running out and into the other socket. So shall I take it off the other socket that is the spur is taken? And it will only be running an outside light that will go to a FSU and then the power to the FSU from the socket as a spur? The light would only be on when needed, not always.

Thanks

Callum Lord
 
No I am not a sparky, it is in the garage and it is defently a spur you can see the main cable run in to the socket and the spur running out and into the other socket. So shall I take it off the other socket that is the spur is taken? And it will only be running an outside light that will go to a FSU and then the power to the FSU from the socket as a spur? The light would only be on when needed, not always.

Thanks

Callum Lord


Just put a plug on the end of the out side light cable and plug it in???
 
or get a qualified spark to do it right. or by using thinner cable, you could get more of them in. NOT.:drummer:
 
No I am not a sparky, it is in the garage and it is defently a spur you can see the main cable run in to the socket and the spur running out and into the other socket. So shall I take it off the other socket that is the spur is taken? And it will only be running an outside light that will go to a FSU and then the power to the FSU from the socket as a spur? The light would only be on when needed, not always.

Thanks

Callum Lord

Technically, what you've got is a radial circuit feeding sockets. Now there is nothing wrong with this arrangement and there is nothing wrong with more than 2 spurs from one socket. This is a 'Tree' arrangement...... (Very French!)

However, the problem arises when the wrong sized MCB is chosen or the radial is longer than that defined in appendix 15.
Personally, I would suggest that you get someone with electrical experience to look it over for you.

Work in garages/gardens is notifiable to the LBC particularly when changing the characteristics of a circuit by adding extra length...
(which I suppose is what I'm doing by contributing to this thread):44:
 