O
Octopus
UPDATE:
So I went back this morning (after leaving floorboards up etc) to find carpet fitters had tidied up my tools, and hammered the boards back down - which I promptly removed again!
2 1/2 hours later the replacement cable was in, tested and done (Zs now being 0.67 ohms)
I don't think that splitting the ring, getting another MCB and testing 2 circuits would have been much quicker!
Thanks for the input
So I went back this morning (after leaving floorboards up etc) to find carpet fitters had tidied up my tools, and hammered the boards back down - which I promptly removed again!
2 1/2 hours later the replacement cable was in, tested and done (Zs now being 0.67 ohms)
I don't think that splitting the ring, getting another MCB and testing 2 circuits would have been much quicker!
Thanks for the input