rsp84
It took the council about 5 days to change a bath over, change the basin taps and tile round the bath, halfway up the wall...
The decision to chase or trunk will have been made already at a higher level than the sparks and tenant liaison officer so speak to the TLO now and find out what the crack isI would stress the chasing in part with the liaison officer as it is them that the sparks have to speak to about it!
Rauer I'm not saying it doesn't happen mate but in my experience what the housing authority have decided will happen is what will happen. It's just a question of when.
One lady who was due a rewire refused, according to her family she had OCD about cleanliness. Eventually she was told if it didn't happen she would be evicted, after a lot of tooing and froing the housing company moved her into temporary accomodation and everything was done.