B
BluSparx
Job quoted in January, started in February on 1st fix
plasterer and other trades supposed to be in at end of feb and me to do 2nd fix in 1st week march.
Payment was upon completion however I feel I have been fair and reasonable as the customer had assured and signed contracts to say that I would have access to complete 2nd fix in March.
After several ignored telephone calls over the last few months I have sent an invoice and covering letter saying that due to no contact and not being able to gain access to complete the work find enclosed invoice for 1st fix. No further work to be undertaken until this has been paid - I personally think 6 months takes the biscuit.
Letter was recieved last Thursday I recieve a call today saying not paying until complete but not sure when the plastering will be completed as it "is a family friend doing it"
Would you send a final demand or just issue claim against customer?
plasterer and other trades supposed to be in at end of feb and me to do 2nd fix in 1st week march.
Payment was upon completion however I feel I have been fair and reasonable as the customer had assured and signed contracts to say that I would have access to complete 2nd fix in March.
After several ignored telephone calls over the last few months I have sent an invoice and covering letter saying that due to no contact and not being able to gain access to complete the work find enclosed invoice for 1st fix. No further work to be undertaken until this has been paid - I personally think 6 months takes the biscuit.
Letter was recieved last Thursday I recieve a call today saying not paying until complete but not sure when the plastering will be completed as it "is a family friend doing it"
Would you send a final demand or just issue claim against customer?