Ze is a measurement with just the suppliers earthing conductor performed at the main incoming point (usually the first DB, C/U)
Zs is a measurement usually at the end of a circuit, fitting, accessory to confirm compliance with Zs values.
Zdb is performed at a sub board. This will measure the earth path prior to the board your measuring at. This could be through numerous other boards.
I think that's right? :-/