Things I can remember off the top of my head...
For installation - On the day you'll get given a folder called 'Candidate Guidance' - read it carefully as it spells out everything for you: what cables to use for which circuits, what protective devices to use, how to mount accessories etc. It is your bible, refer to it constantly. They don't try to trick you, only to ensure you can work safely and follow a specification.
For inspection and testing - they want to see you understand the process and will ask you to write out calculations on the back of your test schedule, so be familiar with your continuity of ring final circuit calcs, and also the motor thermal cutoff calcs. Add notes for how you know values are acceptable - ie max permissible Zs values checked for compliance against table A4 in GN3.
Fault finding can be tricky but you have diagrams to illustrate the circuits to be tested so break them down into sections and work along the circuit methodically. Unfortunately fault finding is one of those things that mostly benefits from experience but in principle you can just apply the same test procedures you used earlier and this should get you most of the way. You have to state the type of fault, exactly where the fault is on the circuit, and how you would fix it. Don't forget the final step for each fix is to retest to prove the fault is cleared and the circuit is compliant.
The grading system is similar to a driving test, with some minor errors being acceptable, but anything that could be interpreted as dangerous will be marked more severely, so pay extra attention to anything involving earthing and protective devices.
You'll have to do 2 sets of safe isolation, both of a whole installation and for individual circuits - and also a short online test which is very straightforward (open book, they provide all the reference materials).

That's a lot of words I just wrote... I'll add some more specifics if they come to mind.
Good luck, the time goes quickly!