I am installing a micro-brewery in our barn in France; as you can guess that, means that I am a brewer, not an electrician I did 'fess up to being a DIYer when signing on.
The brewhouse runs on 3-phase, both for the 12kw heating elements and for the pumps. All use a delta configuration i.e. 3 phases, no neutral. It came from the UK, one brewer was upsizing his equipment, so we bought the old for our new brewery.
I am organising the distribution panel and wiring for the barn, once installed our local electrician will give it a check over and then arrange for inspection and a certification check.
I am trying to reduce both costs and especially waiting time by taking on as much as I can. In France it is particularly hard and time consuming just to get a quote, and there is a huge range in the price of materials.
The brewhouse runs on 3-phase, both for the 12kw heating elements and for the pumps. All use a delta configuration i.e. 3 phases, no neutral. It came from the UK, one brewer was upsizing his equipment, so we bought the old for our new brewery.
I am organising the distribution panel and wiring for the barn, once installed our local electrician will give it a check over and then arrange for inspection and a certification check.
I am trying to reduce both costs and especially waiting time by taking on as much as I can. In France it is particularly hard and time consuming just to get a quote, and there is a huge range in the price of materials.