as engineer says i have no doubt 60A switched fuse is nore than enough an i agree.. 8.5kw shower is max load..

its just knowing what way nie power supplier will split head for me and add meters
 
ok so the landlord just bills them???? i dont think hed like that but its something i didnt know you can do.. its good talk about what i into
 
To split the supply in a house to 2 flats in England, you would normally need to speak to UK power networks.
They will require you to confirm the loadings of each flat (& lanlords supply if required).
They will then confirm incomming supply is big enough. You then create a MPAN with either UK Power Networks or your supplyer, who will then install meter(s) once you can show a completed test sheet.

Takes approx 2 months start to finish.

Hope this helps.

Simon
 