I do/did kitchens regularly. Helps if you know & get on with the kitchen installer.

Invariably, as seems the fashion these days, the kitchen ceiling is getting skimmed, so normally drill access holes or take down small sections of plasterboard, and re-instate (catered for in quotation), to facilitate any rewiring etc.

Quote specifies whats included, anything else is on day rate as an extra.

Normally include the connecting up of appliances. I also allow some extra time, to factor in the time when the painter or floor layer etc etc, overruns.

Personally, I would quote separately for the kitchen & CU replacement, even if the former is dependant on the latter. My quote would probably be slightly higher, than quoted. CU & bits is £200ish, other materials say £200, that leaves £1100. Which with my maths is not quite two days labour :eek:

Edit: hang on I got that wrong, recalculating!

Alright 5 1/2 days, still allow bit more for buggeration :)
 
Last edited:
I would put in a rcbo board, they can be picked up relatively cheaply now even double pole rcbo boards. If not a massive kitchen/utility, I would suggest that the client takes out the ceiling out completely, makes things far easier and less chance of hitting pipes etc, The cost of slapping up a few boards of plasterboard is usually saved on labour and faffing about by plasterer,electrician, decorator. Build a loom in with lighting plugs to plug the down lights in after plastering and painting, draw a decent drawing of where the cables are to be found. The client will change their mind halfway through so build in some extra labour to cater for this.
 
Nothing wrong with a 100mA time delay on a RCBO board on TT IMHO
If RCBO's are single pole that's a pointless exercise, it's a terrible design idea. Most RCBO's on UK market are Single Pole Solid Neutral and manufacturers state not to use on a TT system.

That's why I generally fit Dual RCD Boards, and dump the Main Switch for a 100mA Time Delayed RCD.
 