I do/did kitchens regularly. Helps if you know & get on with the kitchen installer.
Invariably, as seems the fashion these days, the kitchen ceiling is getting skimmed, so normally drill access holes or take down small sections of plasterboard, and re-instate (catered for in quotation), to facilitate any rewiring etc.
Quote specifies whats included, anything else is on day rate as an extra.
Normally include the connecting up of appliances. I also allow some extra time, to factor in the time when the painter or floor layer etc etc, overruns.
Personally, I would quote separately for the kitchen & CU replacement, even if the former is dependant on the latter. My quote would probably be slightly higher, than quoted. CU & bits is £200ish, other materials say £200, that leaves £1100.Which with my maths is not quite two days labour 
Edit: hang on I got that wrong, recalculating!
Alright 5 1/2 days, still allow bit more for buggeration
Invariably, as seems the fashion these days, the kitchen ceiling is getting skimmed, so normally drill access holes or take down small sections of plasterboard, and re-instate (catered for in quotation), to facilitate any rewiring etc.
Quote specifies whats included, anything else is on day rate as an extra.
Normally include the connecting up of appliances. I also allow some extra time, to factor in the time when the painter or floor layer etc etc, overruns.
Personally, I would quote separately for the kitchen & CU replacement, even if the former is dependant on the latter. My quote would probably be slightly higher, than quoted. CU & bits is £200ish, other materials say £200, that leaves £1100.

Edit: hang on I got that wrong, recalculating!
Alright 5 1/2 days, still allow bit more for buggeration