I'll ask once more then give up.
In what context does this apply, an EICR, alterations, something you have come across, a question someone has asked or something else?
We need to know to give an opinion.
 
This is proving harder than finding hens teeth..What would you do if you came across this situation??
Please explain and give us some context as this thread isn't helping anyone with the lack of information.

Otherwise I'll just close it and we can all move on.
 
Let's assume that poor old @EddieB who's being given a bit of a battering has just come across this in a customer's house, as he's been asked to replace a light switch. He's replacing it with another plastic one. The existing one was faulty.
 
Let's assume that poor old @EddieB who's being given a bit of a battering has just come across this in a customer's house, as he's been asked to replace a light switch. He's replacing it with another plastic one. The existing one was faulty.
Well Eddie, in this case I would just change it. it's better to have a switch that isn't broken. I'd also advise the householder it would be a very good idea to get them rewired (if there is no earth on all the other lights too)

What's that you say... It's now an EICR. In that case I'd code it C2 if there were any class 1 fittings and C3 if they were all class 2.
 
Well Eddie, in this case I would justify change it. it's better to have a switch that isn't broken. I'd also advise the householder it would be a very good idea to get them rewired (if there is no earth on all the other lights too)

What's that you say... It's now an EICR. In that case I'd code it C2 if there were any class 1 fittings and C3 if they were all class 2.
Yup plastic switch with endcaps on the screws, issue minor works certificate so it's documented. EICR same codes er maybe C1/2 on class1
 
If. you came across a dwelling with no cps in the switchdrops what would you advise the customer
I would advise that it should have a cpc. Depending on the circumstances would depend on how strongly I would advise. It may be a case of "you really should" or it may be a case of "you must". But there's not really much detail to go on.
 
Requirements for CPC's in lighting circuits were introduced in 1966; if there is evidence of any alterations or additions POST 1966 would this warrant a C2 ? As these alterations/additions would not have conformed then and so don't now either ! Edit they might have done if that alteration/addition was earthed itself
 
Last edited:
Requirements for CPC's in lighting circuits were introduced in 1966; if there is evidence of any alterations or additions POST 1966 would this warrant a C2 ? As these alterations/additions would not have conformed then and so don't now either ! Edit they might have done if that alteration/addition was earthed itself
The safety of an alteration or addition has nothing to do with whether it was permissible or impermissible at the time of installation.
 
The safety of an alteration or addition has nothing to do with whether it was permissible or impermissible at the time of installation.
What i meant - if it was installed pre 1966 and no changes to circuit have been made since then its a C3. But would it still be a C3 if additions/alterations have been made to the circuit since 1966 where these additions/alterations did not use a cpc or other means of cable protection ? It was more of a question really, hope its relevant
 
What i meant - if it was installed pre 1966 and no changes to circuit have been made since then its a C3. But would it still be a C3 if additions/alterations have been made to the circuit since 1966 where these additions/alterations did not use a cpc or other means of cable protection ? It was more of a question really, hope its relevant
Well assuming that they were installed in a like fashion it's hard to see how a credible argument could be made that the newer wiring is less safe than the existing. But I'd be concerned about 1966 wiring in fairness as that is essentially 60 years old.
 