You are almost into rewire territory with that number of points, I would tend to price it on that basis, excluding the kitchen, etc.
As you have not seen it you cannot plan cable routes, furniture moving, type of flooring, type of walls, any other trades, so you will be at a bit of a guesstimate level whatever.
Work it out based on your expected parts plus labour basis add £400 for travel etc and then add another day for all the problems, and another £100 for getting parts, planning that you may need to encompass on site.
Then work it out based on say a price per point, cost of fuel plus contingency basis and compare the two.
Choose the middle ground and you should be somewhere near.
Include in your quote "any unanticipated structural or technical problems encountered will incur additional charges at the following rates..." or being nice "this price may vary once I have made an on site assessment, all changes will be advised asap"