Depends. 2 up 2 down or factory ?
I would do a domestic property up to about 8 circuits for £150. That's definitely a minimum price though. Am helping do a social club of about 80 circuits this week, some wiring dating back 50 years probably. The guy that priced managed to negotiate a day rate for that as no previous results and precious little marked up, so too many variables to give a fixed price.

36 circuits , mechanics garage Sunday only 8am
 
You have to fully test and inspect 36 circuits in one Sunday ? LOL.

It'd take most of the day to find and disconnect all the loads and neons! A mix of three phase and single, bench supplies, 12v transformers, motors, high bay lights, heaters, the office, canteen, FSUs and the list goes on.

You'll need more than two to do it in a day.
 
It'd take most of the day to find and disconnect all the loads and neons! A mix of three phase and single, bench supplies, 12v transformers, motors, high bay lights, heaters, the office, canteen, FSUs and the list goes on.

You'll need more than two to do it in a day.
Really?? i disagree, youve noted a list of problems that could indeed not be there. You could do that easily in a day between two people IMO
 
It'd take most of the day to find and disconnect all the loads and neons! A mix of three phase and single, bench supplies, 12v transformers, motors, high bay lights, heaters, the office, canteen, FSUs and the list goes on.
You'll need more than two to do it in a day.

Only got reception office 2 4post ramps 1 2post Ramp roller shutter door, 4-6 lighting circuits and toilet area
 
Yeah , two sparks a Sunday
sorry. 20 circuits 8 three phase

Ah that sounds better. 2 blokes should bob that off in a day depending on the site. What size is it ? Easy access to everything ?
Dunno really as I never work a Sunday. Overtime rate for a pair for a day plus something for writing up time ?
Some lads on here say between £20 and £30 per circuit. Of course that's not Sunday rates though.
 
It'd take most of the day to find and disconnect all the loads and neons! A mix of three phase and single, bench supplies, 12v transformers, motors, high bay lights, heaters, the office, canteen, FSUs and the list goes on.

You'll need more than two to do it in a day.

took 20 minutes to visually look for equipment vulnerable to testing was only the pc and cctv that needed removed , all 3 phase isolators in off position for ir test and in on position for eli test.

so what price would you have given based on your statement ??
 
garage not in operating hours , not the largest but garage area had 7 cars in it so access :s hmmm .

- - - Updated - - -

id be looking for 15 quid a circuit. 3 phase would count as 3 circuits though.

charged £10pc, and counted 3 phase circuits as 3
 
Yes really.... 10 circuits per man.... thats nearly an hour a circuit

So you're going to work ten hours on a Sunday, at £15:00 an hour? Do you work as far South as Birmingham? If so I have some work I can sub to you.
 