A customer has had a mare with their kitchen install which one of our Eastern European friends working for a builder who's since gone bust did, you know the scene.
The pic attached isn't great so I'll try and explain what's what & any advice on how to sort it would be appreciated.
The first way from the RCD on left is 40a with the 6mm cooker circuit & the 2.5mm kitchen sockets in.
Then there's a couple of 2.5mm RFC's (brown) followed by what I think is 3 more RFC's (red) spread over 2 MCB's, you need to switch off both to isolate these circuits so they're obviously cross connected, I think these were shoved in there to make way for the additions.
Then there's a selection of lighting circuits & an immersion.
Ideally I'd like to put in a new 16way CU but space is really tight due to the gas & water services in the vicinity so what can I do to sort this mess out? I will be replacing the trashy CU but can I double up any circuits and still give them full protection?
The pic attached isn't great so I'll try and explain what's what & any advice on how to sort it would be appreciated.
The first way from the RCD on left is 40a with the 6mm cooker circuit & the 2.5mm kitchen sockets in.
Then there's a couple of 2.5mm RFC's (brown) followed by what I think is 3 more RFC's (red) spread over 2 MCB's, you need to switch off both to isolate these circuits so they're obviously cross connected, I think these were shoved in there to make way for the additions.
Then there's a selection of lighting circuits & an immersion.
Ideally I'd like to put in a new 16way CU but space is really tight due to the gas & water services in the vicinity so what can I do to sort this mess out? I will be replacing the trashy CU but can I double up any circuits and still give them full protection?