Ok, I just have to ask. The council electrical engineer that gave the contractor the work and was over-seeing the project. Was he blind? Or was it one of those self funding schools where they suit themselves?
 
A good point, the job had a 5% retention held over it for a 12 month period, the job was completed 11 months ago, the school however handed over all the money after they were told works were completed and the company concerned think the works are satisfactory, the school apparently are going to mention the Job to the county council and hope they force the electrical contractor to return to site and put the work right, I am awaiting news still of the outcome, I have been paid for the report and may never find out what happened unless I pop into the school again one day and talk to the head and take a look to see if they did return. There is a possibility I may be asked to go back and secure the cabling properly to the wall, time will tell.
 
i wouldnt let them back, and the power of goverment money being stole will make them pay for repairs....
 
i would send the pics to the boss of the company that "installed" it and ask for a responce

I don't need to do that fella, I did a report with photos for the school with my recommendations, it's their call how far they take it.
 
but to the guy who gives out the work, needs sacked too, but then again its probably a mate, backhander
 
i wouldnt let them back, and the power of goverment money being stole will make them pay for repairs....

I expect they will go back when the county coucil calls them about it through embarressment, I als expect the school will never release a retention early if they have works carried out on this Jobs scale again, the Job was a 30 grander, and this is what they got for their money.
 
but to the guy who gives out the work, needs sacked too, but then again its probably a mate, backhander

several companies priced the works, the company who did the job actually won the works by 800 pounds on a 30 grand project, the arcitechs running it had no electrical engineer involved and the school didn't know anything was amiss, when I went to do a inspection it was for the 4 yearly report required in the school on the main on peak system, in theory I need not have got involved with the off peak at 11 months old, but I couldn't let it go. I wonder how the contract manager of the company who handed the manuals over on completion will feel when he is called to explain this to his President haha.
 
it looks worse than my work in 1st year, telling you im geting good at this and enjoy it when looks good/smart
 
several companies priced the works, the company who did the job actually won the works by 800 pounds on a 30 grand project, the arcitechs running it had no electrical engineer involved and the school didn't know anything was amiss, when I went to do a inspection it was for the 4 yearly report required in the school on the main on peak system, in theory I need not have got involved with the off peak at 11 months old, but I couldn't let it go. I wonder how the contract manager of the company who handed the manuals over on completion will feel when he is called to explain this to his President haha.
well.....given all the squabbling and fighting for/snatchin jobs from under each others noses that`s goin on nowadays......folk`l end up walkin for that standard of `install`......
 