S

Steve1968

I have recently replaced the DB in a house I completed the installation test on the new board but client also wanted the off peak board tested. Would I need to do a EICR for off board or include test results as part of installation certificate. If it is included what is classed as the main switch as there is 2 boards. Thanks
 
do a seperate EIC for the board on econ7

and whilst your at it can you please re-issue the client with an EIC for the works you have carried out....


such as the dis-board change....
 
He said he's doing an installation cert. eicr for e7 board should do if alls you have done is tested it.
 
I. Would I need to do a EICR for off board or include test results as part of installation certificate. If it is included what is classed as the main switch as there is 2 boards. Thanks
If it is an existing board and you have not touched it in any way, and the client wants a condition report then yes crack on.
 