Righto not entirely sure what to do certification wise.

Job is upgrade of main earth and main bonding.

I was thinking an installation cert without a schedule of test results as I am not touching any circuits.

and secondary is this notifiable I'm thinking yes but may be wrong.

Never done this job on it's own before always been tagged onto a fuseboard change or additional circuit.

EDIT:

now i'm thinking.....

Zs at fuseboard would be required....

schedule of test results required then.
 
I'm thinking EIC with SOTR for the continuity readings of your bonding mate.
Now where did I put that tin hat
 
In this situation then I think maybe a written letter explaining the job, with relevant calcs, and BS7671 table refs. A EIC may look like a blank price of paper if it's just bonding/earthing listed. Remember other forms are not precluded, provided no less information is provided.

- - - Updated - - -

In this situation then I think maybe a written letter explaining the job, with relevant calcs, and BS7671 table refs. A EIC may look like a blank price of paper if it's just bonding/earthing listed. Remember other forms are not precluded, provided no less information is provided.
 
I'm thinking EIC with SOTR for the continuity readings of your bonding mate.
Now where did I put that tin hat

That sounds like a plan!

Ta.

In this situation then I think maybe a written letter explaining the job, with relevant calcs, and BS7671 table refs. A EIC may look like a blank price of paper if it's just bonding/earthing listed. Remember other forms are not precluded, provided no less information is provided.

- - - Updated - - -

In this situation then I think maybe a written letter explaining the job, with relevant calcs, and BS7671 table refs. A EIC may look like a blank price of paper if it's just bonding/earthing listed. Remember other forms are not precluded, provided no less information is provided.

I'll do that too.
 
Whether it's notifiable or not mate surely he should leave some record of having been there and carried out some work
 
Oh, yes. I'm not disputing. I agree with EIC. Earthing conductor obviously very important.

It's just that he asked if it was notifiable and no one answered this
 
Last edited by a moderator:
if its any help i read in one of the NIEIC books a Minor works cert covers installation of main equipotential bonding conductors and suplamentary bonding conductors,
 