S

SensesFail

I have a mates brother needing some work doing in the newcastle area. I'm trying to price it but don't want to out do myself or on the other foot charge too much to a mate in effect. The work is:

Change a consumer unit (10 ways)
Sort out earth to gas and water
Move a light
Add 2 sockets in a bedroom.
Test whole installation

I was thinking 300-350. Does that sound too much?
 
That is cheap. I'd charge £600 for that. So I'd say something in the middle as its 'mates rates'
 
I'd probably charge that to a good mate but not the brother/friend of a mate.

But then I have just charged a customer £80 for a day and a halves work so my estimating skills obviously need improving..... :(
 
Don't discount mates or family - you are doing this for a living, not a charity.

If anything say you'll do the LABC notification for free so they think they are getting a discount.
 
Far too cheap and it's not your mate, it's his brother so unless he can return the favor I.e he's a mechanic etc then it's two days labour £150 a day??? I guess as youve not put any description down. Plus materials roughy £150-£200?
By the way it's just an educated guess
 
that's stupidly cheap.

without testing first, you could end up being on the job for days if the installation is riddled with faults that will only be shown once an RCD is connected to the circuit.

at least £500+ for the board change and testing

£60 a socket outlet

at least £150 for bonding (unless its really close to DB)

etc...

materials would cost more than £300 ? lol
 
I have a mates brother needing some work doing in the newcastle area. I'm trying to price it but don't want to out do myself or on the other foot charge too much to a mate in effect. The work is:

Change a consumer unit (10 ways)
Sort out earth to gas and water
Move a light
Add 2 sockets in a bedroom.
Test whole installation

I was thinking 300-350. Does that sound too much?
so, why dont you want to do it?....
 
well for a start....gas & water are extranoius....and as such are bonded......so get your terminology rite....if your gonna come in here....
rite...to business...
new C/U...cert n test (a definate)...£300
then theres movin that lite.....£????...put it on time £25 per hour plus materials...
gas and water bondin....depends....are they in close proximity(ish) to each other?...if so then go from ext one to ext 2....keep it continuous.....that keeps the cost of cable down....whilst still being compliant.....hmm....put £80 on it...
2 more points in bedroom.....go for £35 a point....just to cover your arse......
and so that little lot adds up to....

£485......
 
I know !! I wouldn't even bother getting out of bed lol

I charged £550 last week for a 8 way CU change

In London though lol
 

OFFICIAL SPONSORS

Back
Top