I chose 5 seconds, but the 'correct' answer is 0.4ms apparently...That is also a big dodgy.
For a TN supply it is 5s sub-main or 0.4s for a final circuit. But the one you ticked was 0.4ms which is not feasible for a 50Hz supply!
I chose 5 seconds, but the 'correct' answer is 0.4ms apparently...That is also a big dodgy.
For a TN supply it is 5s sub-main or 0.4s for a final circuit. But the one you ticked was 0.4ms which is not feasible for a 50Hz supply!
Well they have a mistake in the list!I chose 5 seconds, but the 'correct' answer is 0.4ms apparently...