- If you're a qualified, trainee, or retired electrician - Which country is it that your work will be / is / was aimed at?
- United Kingdom
- What type of forum member are you?
- Practising Electrician (Qualified - Domestic or Commercial etc)
I would stuck with the original plan and fit a new sub board for your circuits and leave the rest to be sorted by whoever fitted it and don't get involved with it. If client insists you change board I would walk away
I agree with this . No need to walk away , Explain you won't certify and take responsibility for work completed by other contractors . You could fit a new board large enough to accommodate a mains change whilst connecting only your circuits .