Here you go.Just curious have you sat your AM2 exam ? If so you got any hints and tips on passing?
The AM2 and what to expect.pdf
Here you go.Just curious have you sat your AM2 exam ? If so you got any hints and tips on passing?
There is no requirement on the AM2 to carry out any bonding of the pre-installed containment/tray etc. Unless the assessor syas otherwise, don't bond it.I underatand that the containment systems are already in place but, surely that means I can still bond it to the MET etc. Surely I wont just leave it?
you don't bond trunking, you earth it as it is an exposed metal part and may or may not form part or all of the cps/s for the circuit/s within. tray normally carries sheathe cables and as such would only need bonding if it were extraneous.[/QUO
Why?Said before Ian you will get in trouble doing that![]()