Hello All,
Currently building an extension to my barn/workshop and before i pour the foundations i want to run some new cables from my ground mount system which will eventually go through the barn and then into the house.
The run comprises of:
i) 25m Buried from the array inverter to the barn
ii) 20m Clipped to cable tray throughout the barn (perforated horizontal)
iii) 18m Buried from the barn outlet to the house CU
So from my limited knowledge:
4000 watt / 230 v = 17.39 Amps
Maximum Volts Drop = 5% = 11.5 Volts
And Im guessing reference method for CCC is:
i) D (number 72)
ii) F (number 31)
iii) same as i)
Before i carry on, am i barking up the right tree?
As ever, any help really appreciated.
Cheers, C.
Currently building an extension to my barn/workshop and before i pour the foundations i want to run some new cables from my ground mount system which will eventually go through the barn and then into the house.
The run comprises of:
i) 25m Buried from the array inverter to the barn
ii) 20m Clipped to cable tray throughout the barn (perforated horizontal)
iii) 18m Buried from the barn outlet to the house CU
So from my limited knowledge:
4000 watt / 230 v = 17.39 Amps
Maximum Volts Drop = 5% = 11.5 Volts
And Im guessing reference method for CCC is:
i) D (number 72)
ii) F (number 31)
iii) same as i)
Before i carry on, am i barking up the right tree?
As ever, any help really appreciated.
Cheers, C.