Hi all, in much need of help regarding part p and its rules and regs, I'm a qualified spark (2330, nvq3 and 17th) and have had some re-wires coming up, I am more than capable of doing the work and was going to get my mate who has napit to come test and certify the work until I get my 2391 and napit or niciec. Is there any problems with this?? Any feedback will be very appreciated
 
I'm not the most experienced person on this matter but as far as I'm concerned, there's nothing wrong with that...assuming your mate is willing to sign off your work.
 
Unless he is supervising and guiding your work at every stage and is prepared to then sign that he has completed the design, installation and inspection and testing then he would be performing an illegal act as the self certification schemes are SELF certification, unless you are a qualified supervisor for a designated company.

I am not saying it does not happen and, from the 6th April, (if the capability is available) electricians registered with a third party sign off scheme would be able to perform an EICR on a new install to provide the notification to building control, however the scheme arrangement's have not yet been decided by the scheme providers.
 
Thanks for the replies, how and where do you go to get in 4 days? niciec want to see 2391 and napit wants you to have 2391 within 12 months of becoming a member I don't mind taking 2391 but may take some time but I need to be able to sign of ASAP
 
Like you said, Napit require 2394/2395 within 12months...which i think is very reasonable. Get your head down, crack on with the studies and you'll soon reap the rewards in the near-future by knuckling down with some hard revision.
 
2391 no longer exists , ended last xmas.
you do not need 2391 to join nic.
you can issue any electrical certificate without joining any scheme.
 
2391 no longer exists , ended last xmas.
you do not need 2391 to join nic.
you can issue any electrical certificate without joining any scheme.

What do you mean?
You can issue the certificate but just not notify or do you mean you can issue an EICR?
 
Qualified electricians are still the same as they always were. You can do everything you used to do. The only change part P brought about was that some jobs have to be notified to LBC by law. This can be done by either joining a Part P scheme and signing the work off yourself, or by letting the Council know in advance, paying a large fee and letting them take responsibility for signing off the work. Because this is pretty much unworkable (with most Councils not having the appropriate manpower), there will be a new system of letting other registered electricians do what the Council used to (on occasions) do.
You, as the qualified and competent electrician, still fill in the certificates you always have done.
 
So will this qualified electrician who signs off other peoples work be liable for the quality of the work or will they just be there to inform the council?

If I am not registered but qualified and my work is to a high standard and fully compliant with BS7671 and for example I do a fuse board change, carry out all my tests and complete an EIC will I be held responsible for any faults that may occur later due to poor workmanship or will the registered electrician who signed the work off be held liable?
 
the certificate has 3 signatures !

design

construction

testing and inspecting

you could have 3 different people if you wanted !
 
for example I do a fuse board change, carry out all my tests and complete an EIC will I be held responsible for any faults that may occur later due to poor workmanship or will the registered electrician who signed the work off be held liable?

the tester / inspector who is signing off your work should do the EIC.
 
So it's the tester and inspector who is ultimately liable if the work carried out by someone else proves to be substandard in the future.

It's a hell of a responsibility if you didn't build it yourself.

But what if you issue an EIC and don't inform building control because you are not in a scheme.

What will be the consequences of this omission?
 
So it's the tester and inspector who is ultimately liable if the work carried out by someone else proves to be substandard in the future.

It's a hell of a responsibility if you didn't build it yourself.

But what if you issue an EIC and don't inform building control because you are not in a scheme.

What will be the consequences of this omission?

Very little, as has been the case with people still doing jobs in their own homes without notifying LABC, and they haven't ended up alongside Chris Huhne in Leyhill.....

And yes a major responsibility signing off another's work, and to think of some of the DIY failures you see from time to time, alot will be refused to be signed off!
 