mattg4321

~
Arms
I don’t do loads of commercial work and when I do it’s normally smaller jobs, less than £10k that are fed to me by builders I work for. I don’t really have to price for them in the same way as this upcoming job.

Been asked to quote for a fairly large (to me anyway) council job. Been sent a pricing document to fill in. Mostly a load of -------s really. Itemising prices for each individual element is almost impossible imo. Price for installing containment. Price for wiring lighting. Price for fitting lighting etc etc. Surely a total price and what’s included should suffice. Anyway, I digress.

Lighting costs have already been filled in. Don’t know if I could get them cheaper through wholesalers but the pricing document is asking me for my markup percentage. Materials cost is circa £30k. Normally I allow 20% on top but would like to what is normal for this sort of work. Cheers
 
Its probably a "Bill of Quantities" in which case it's needed to be filled out so that payments can be made against work done, these quantities will be measured by the QS (Quantity Surveyor) at the end of each month against your monthly invoice to authorise payment, don't worry too much about it, just use sensible costs against each item, wiring lighting would be per linear metre etc:

At tender stage it's the total cost that is looked at, also as it's council you can be sure that lots of alterations will occur during the project and daywork's will be paid against those alterations your daywork rate should be a percentage over and above your normal rate and is where you make your profit, therefore offsetting any low costs you may have accidentally used.
 
Last edited:
"Not in the contract mate, that's extra's" is literally how EVERYBODY ever makes any money on these gigs.
 
10% tops on listed mats and sort your labour prices out to suit.

The end price is what counts, so rough cost it your normal way and compare.
 
Thanks for the thoughts guys. I think there’s a fair chance I’ll get it anyway as my costs will be part of a builders I work for. He seems to be pally with the right people.

I’m not too fussed if I don’t win it. Just don’t want to be the reason he doesn’t if my markup on listed materials is thought to be excessive. I’ll bump the cost elsewhere if necessary.

We’ve had between 10-30% here so seems my 20% isn’t far out?
 