What i would do (as a qualified electrician) is log onto a controversial forum for 'electricians' then ask fundamental questions that I should already know the answers to (as a qualified electrician) which i will then ignore in order to prove that I AM A TROLL.
 
was just looking for some advice as I don't normally work on domestic installations didn't realise it was a crime
 
was just looking for some advice as I don't normally work on domestic installations didn't realise it was a crime
but surely you know and understand about IR, segregation of circuits and RCDs/RCBOs?....
further more you must have an inkling that its notifyable work.....
i think what it is ...is that just lately theres been so many shyte posts/threads that a lot in here are on edge..wary ..whatever you want to call it...
 
yeah I do but when I have been looking to buy a new CU I just couldn't decide between a split load or using RCBO's instead.
 
RCBOs are better as they are all singing and all dancing and minimise inconvenience to the user better by providing individua protection for each circuit but are more expensive
dual RCD boards are a cheaper way of complying with the 17th regs
as you have limited number of circuits then i would go with RCBOs then any problems it will be localised to one circuit and easily identified and rectified as well as minimising loss of supply to other circuits and provide better protection

as your paying and your the user the option is yours this job will be notifiable under part P if you are going to bother notifying LABC either directly or through a scheme being a competent person of an assessed enterprise
 
Last edited by a moderator:
either or is acceptable...it more often than not comes down to how much room you have for the new C/U....this will of course dictate split load Vs 8 way etc...
just be aware wont you that (and i think it has already been mentioned) you may have shared neutrals here to contend with as it was common on the 15th...IR test between neutrals to verify....
 
another thing as well....
better to get some preliminary tests carried out first....arm yourself with a bit of info see...
so a Ze should be carried out to confirm you have a good earth at the property as if not then you will be waiting for the DNO to rectify before any live tests can be carried out....
 
Just a point since your in Scotland we do not subscribe to Part P, And notifiable works are controlled by Building Warrants, If it is a domestic building under or including 2 storey you do not need to notify whatsoever and does not need to be certified. I know Aberdeenshire council and even to a point Aberdeen City are very relaxed on certification even if it was required. Some councils are like nazis i would point to the Western Islands and Orkney Islands as one such example :) I think one of the greatest things is you are not forced into one of those con scheme organisations like ELECSA/NAPIT/NICEIC i fear south of the border they get a rather unfair deal with them.
 
Just a point since your in Scotland we do not subscribe to Part P, And notifiable works are controlled by Building Warrants, If it is a domestic building under or including 2 storey you do not need to notify whatsoever and does not need to be certified. I know Aberdeenshire council and even to a point Aberdeen City are very relaxed on certification even if it was required. Some councils are like nazis i would point to the Western Islands and Orkney Islands as one such example :) I think one of the greatest things is you are not forced into one of those con scheme organisations like ELECSA/NAPIT/NICEIC i fear south of the border they get a rather unfair deal with them.

Don't really understand the way it works in Scotland, but i haven't even really attempted to understand it.

But by not certify, do you mean not give an EIC, EICR, MWC to the client on completion of a particular job? If so, i seriouslly dislike that. But if that's the legal way up your end, then that's the legal way.
 