We agreed at the start for a day of my time. When the first round of issues were found, I gave her a rough idea of cost and the fact it would need an additional day to actually do the testing.

Then on Monday, when more issues were found she got another update. My only failing there was not conveying that in writing.
A mistake many people make, we are far to trusting, a lesson learned maybe?
 
We always submit a costings list for carrying out repairs generally accessory replacement and they have a choice whether to sign up for it or not, they can even put a ceiling limit to it. Sounds like you may have started off doing things you thought wouldn't be a big deal but then it escalated. I personally wouldn't give a discount because I think your price is reasonable but if you want to put this to bed you may want to knock off £50, put it down to experience and forget it we have all been there.
 
OK but you still have to replace what you have used, albeit a small cost, that's still not a bad price, people see you haven't supplied much so they think you are expensive not considering the training, knowledge, at least you have the satisfaction of knowing you have done a good job for a fair price, that's my 4 pennyworth.
That's the problem, "the electrics work so don't need fixing" attitude is ripe. People don't appreciate what they cannot see. Electricians get a raw deal in this respect because all the hard work is usually (domestic installs) hidden. You do a re-wire and all the customers see are a few new switches, sockets, light fittings and a new fuse board for their £2.5K + bill.
Sparky Chick,
you may have to suck it up and offer her a discount on this occasion. But what you can take from this experience is, how important it is to provide the customer with a detailed description of exactly what the are paying for prior to any work commencing. I also update and advise the customer as I'm doing the job of any remedial work that might be found to need doing along with a cost for such. This way there are no surprises for either party concerned when it comes to final payment.
 
The only real leverage she has is that cable damage and the fact we lifted a carpet to find the cable exit from the trunk it was in, I think I'm going to get me a decent carpet kicker and then simply do it myself next time, wouldn't be so bad but I offered to put the floor back down and sort the carpet... "Oh no, you crack on, I'll sort that"

I've written her a letter, explaining I've already saved her £365 by electing to bill her using my day rate. I'm going to swallow the cost this time on the condition she pays promptly, if she don't it's full price.

Suffice to say, I won't be doing it again like this, next time it will be EICR only. Ordinarily that's what I do, but because of the tight timescales, thought she'd be grateful and she agreed. Doubly irritating as I worked way beyond the normal 8 hours that my day rate covers and the implication that despite this being a field where knowledge and thinking is required, your clearly not allowed to think on site because you're not doing anything!

Customers.... who needs em!!! ;)

Lesson learned and thanks for the business insight guys, much appreciated (just wish I could dish out a few likes) :)
 
Yeh I could do with some "likes" cos I have low esteem and it is only the occasional "like" keeping my head above water:(
Your situation must be frustrating especially as you sorted her problems for the house sale but try and move on from it.
 
Go to a local carpet shop not the big ones but the high street type, ask if a fitter is about, most carpet fitters are self employed and will refit a small carpet for £20-£30 cash, do it all the time now as some customers think I might be good at what I do but my carpet fitting is not the same as before I took it up,as in a trade matches a job, the price you have changed is not over the top just reminded her that you did not charge her for the time spent on the brockon cable, and for time spent drinking tea and the the smoke brake
 
Before I lift carpets I always tell the client I need to lift the carpet, give them the option of getting someone in to lift it for them and refit or sign an indemnity as it is liable to be damaged. I always take numerous photos prior to doing any work as well and let the customer see I am doing it, that way when they claim that their 10 year old shagged threadbare carpet had just been laid we have photo evidence it wasn't. I do the same when working in bathrooms for showers etc so when they say you have damaged the bath etc........
She is probably just trying it on, I would tell her I have already discounted it by charging a day rate as opposed to hours worked etc etc, as she doesn't get the eicr until she has paid you and she is not really in a position of strength (oh and head scratching in front of client is not a good idea!:-)
 
Yeh I could do with some "likes" cos I have low esteem and it is only the occasional "like" keeping my head above water:(
Your situation must be frustrating especially as you sorted her problems for the house sale but try and move on from it.
Here's a like for you, "I Like this post^^^^^^^" ;)
 
Yeh I could do with some "likes" cos I have low esteem and it is only the occasional "like" keeping my head above water:(
Your situation must be frustrating especially as you sorted her problems for the house sale but try and move on from it.

Like :)
There you have it,maybe you can breath at little easier for a while :handok:
 
I do like the fact we are liking the likes and everyone is in a like mood, it's like so nice to like and not be a non liking person, would like to give you all a big thanks for all the likes you are giving each other it's like we are all in the same like world it makes me so happy I just want to like you all, but I can't as like to thanks it has gone and now all we can do is report so Ian going to report that I like you all and thank some of you ( sorry beer day with old work colleagues )
 
£720 doesn't even cover working 11 hours on a Sunday!
If a customer asks you to work on a Sunday when it's outside of normal working hours for the sector you are in then it should be at least double time.

I do a lot of work in theatre where Sundays are just another normal working day and yet it is still standard practice to get double time for it.
 
Not been on here in a little while.. good to see familiar (and non familiar!) names still hanging about. Hope all are well..

In a word I would say no....hell no...not in a million years!! Had a customer recently who was buying a house and his mortgage provider wanted the electrics up to scratch before they would approve the mortgage. He was constantly emailing asking for a copy of this and that, and I was constantly prompt polite and helpful so he could get this house. He asked for a discount on the board change. As it was an easy one I said yeah you can have 10% off. After giving him his compliance cert a couple of weeks later I asked him if he could leave a review of my work. Sent the tawt a link and it would have took him less than five minutes to do. Still no review (positive or otherwise!) from him.. so basically, remember you are a business and don't be soft with them. Customers can be like children, given half a chance they will take advantage of you as much as they possibly can.

You have the right approach in stating that you have charged day rates rather than hourly ones. In the customers tiny little minds this can help them to comprehend things from your perspective. And I would make note of the fact that you worked longer than normal hrs too. In reference to keeping the I&T separate from remedials; yes it's definitely good practise, but occasionally time counts against us. In the OPs situ I think that saying I will send a quote for remedials wasn't that practical. And often, as we know, fault finding is a case of 'how long is a piece of string'...
 