I'll post some pics when I get the chance to go there next but is it not the dno responsibility seen as it goes in to there neutral
Are you saying that 40 Flats are without any form of earthing? Who are you doing the EICR for?
You don't know it is a rod or its purpose if any so without these facts you need to use your own judgement as to whether the safety of the installation is being compromised.Remedial works are required within the flat. Good zdb reading in the flat tho I was thinking that as well pme earth rod would that not be a c2?