Wouldn't he be better off getting a spark to do the job ?

Probably...but that wasnt what he was asking,I answered his question. TBH if thats the forum policy we might as well just answer every thread not started by an electrician...."Get an electrician in" and not bother with any other advice.
 
He should't be touching the electrical installation if he's not a spark
probably...but that wasnt what he was asking,i answered his question. Tbh if thats the forum policy we might as well just answer every thread not started by an electrician...."get an electrician in" and not bother with any other advice.
 
Ain't got a problem with DIYers changing fittings and sockets ect, but when it comes to adding any length of cable in an installation we shouldn't be encouraging it despite the fact that "it ain't rocket science", clearly he has no test gear, so telling him to go ahead is like endorsing electrical work with no testing ?
 
I agree. You cant force him hire a spark even if we all know its the best option however i would personally feel better having given someone good advice than some DIYer going in blind or iladvised and being more of a danger
 
Ain't got a problem with DIYers changing fittings and sockets ect, but when it comes to adding any length of cable in an installation we shouldn't be encouraging it despite the fact that "it ain't rocket science", clearly he has no test gear, so telling him to go ahead is like endorsing electrical work with no testing ?

If you read post #37 I told him to go ahead if he is competant to do it to bs7671 ,as some of the earlier posts suggested it would be illegal under part P,which is not the case.....thats not telling him to go ahead and ignore 7671.
 
He doesn't seem competent to me lol
If you read post #37 I told him to go ahead if he is competant to do it to bs7671 ,as some of the earlier posts suggested it would be illegal under part P,which is not the case.....thats not telling him to go ahead and ignore 7671.
 
The OP has been given the option to pm me with his phone number via a pm to him if he wants this done. If not, that is on his head. Lets list the things that we would look for before we reach for a reel of cable....

What earthing arrangement is it, bonding, rcd's??? Ze test, Zs on existing circuit whilst energized using a checkabox. In the cu see if its one or two cables on the mcb, end to end tests, R1+R2, IR test, is the mcb the correct ratting for the cable, is the cable the correct size for the load and the extra load? Now he can look at extending it (once we now if its a rfc or a radial).

Then all we have to do is install the new sockets within zones and within the part p regs, do most of the above tests, issue a cert and sleep well at night knowing its a job well done.

After all, its only a few extra sockets, whats so difficult??????
 
For you and me and most, not all, but most sparks, nothing haha

MDJ is it only me that does a CSI crime scene lay out in my head for anything that I'm working on? You know like what the CSI programs do recreating the murder, I do that with electrics whilst the customer is on my shoulder asking what is wrong. Most of the time its diy'ers and they dont tell you until the last minuet and complain about the bill for the time its taken you to find it! Arh.

In this thread, the customer that wants to do it himself does not have the full knowledge to complete his task hence why he is asking on here and why he should leave this project alone. As we all know, its not that simple unless you know what your doing.
 
When did it become the responsibility of people posting on forums to protect the lives of the criminally thick/tight? If someone's to dense to take the advice they're given, or to accept that they're out of their depth then it's just nature's way of cleaning out the Gene pool.
 