When doing a CU change you must also do a check of the property before hand, asking the client of any alterations/additions - seeing if there are any broken fixtures and fittings. Followed by checking main earthing is up to scratch and bonding is present where appropriate (if it's not up to current standards, it needs to be upgraded) And an IR test is a must between N-E.

So, its not just a matter of slapping a new CU on.

P.S. An Electrical Installation Cert takes the best part of a day on it's own.
This makes me laugh eic takes best part of a day are you for real were do you get this from
 
This makes me laugh eic takes best part of a day are you for real were do you get this from

Done properly and filling out the cert - yes, it takes the best part of a day.

How long does it take you to do a EIC with certificate then? And we're talking doing it properly here....
 
Am i going crackers here...theres no way you can carry out the full testing procedure, properly, and fill out the EIC certificate in 2hours.
 
Just banged it through our spreadsheet. 843.67 for labour and materials. That's allowing 3 days
 
that sits right slap bang in the middle of my estimate.
 
I'd do the job for around 600, and worst case 2days work, but I'd be aiming for a days work. And as for a EIC taking a full day, how long would it take you to do an EICR then?

And Glasgow spark, it ain't just youngens that can get some speed up, been doing it for 27 years and I can get jobs done quicker now than when first out of my time, it seems more a case of practice. Some sparks I work with are dead slow with testing, they can take double the time I would take, doing the same tests, it comes down to an efficient way of working and being methodical.
 
I never said a full day, i said the best part of a day.

Obviouslly depends on the size of the install, but quoting 2hours for EIC is optimistic.

Yes methods like a global IR can be done to save time, however, i tend not to bother because 7/10 you'll get a duff reading and have to do everything individually anyway.
 
I'd do the job for around 600, and worst case 2days work, but I'd be aiming for a days work. And as for a EIC taking a full day, how long would it take you to do an EICR then?

And Glasgow spark, it ain't just youngens that can get some speed up, been doing it for 27 years and I can get jobs done quicker now than when first out of my time, it seems more a case of practice. Some sparks I work with are dead slow with testing, they can take double the time I would take, doing the same tests, it comes down to an efficient way of working and being methodical.



i know mate it was tongue and cheek, these guys are deluded 1 day for eic :D
 
Jesus christ i didn't ever say 1 day for eic...i said the best part of a day, which to me is about 5hours if doing a 9hour day which i do tend to do now.

I'm not one to chain out an EIC so i can move onto the next one as quick as possible, wheres the need in rushing, take pride in your work. 2Hours for a proper eic with cert completed too me means going gung-ho - which is when corners can be cut. Not for me thanks.
 