BluSparx

I am apparently too expensive and too slow

the situation is

6 x 2 gang sockets fed via a 4mm radial
1 x cooker dual appliance outlet fed via a 10mm radial
5 x collingwood firerated fixed downlights (had to be collingwood wouldn't take halers)
Installation of 10mm2 equipotential bonding to both gas and water
6 x under cupboard strip lights

kitchen is being completly ripped out, - I don't need to patch as once 1st fix completed is getting a full skim.

I quoted 2 days labour - 1 day for 1st fix, and 1 day for second fix once units and plastering all complete

The guy states that I should only charge him for 10 hours labour as he reckons somebody else can do the same job in 10 hours (7 on day one and 3 on day 2)

My issue is that I can't get in till 10am on 1st fix and on 2nd fix will be around 11am so I can't get a decent size job in - I'm prepared to tell him to get the other guy but does anyone think I'm being unreasonable quoting 2 days labour.

Total quote for the whole job came in at just over 1200 before anybody asks that is parts & labour.
 
To be truthful pal think your price is bang on for labour and materials
Like you say can't get in till 10/11am so that's morning screwed and by time you've completed not leaving much time to do any other job so I think what you've quoted is right pal
 
Thanks I just wanted to check you know when you start questioning yourself but I thought 2 days labour purely down to the fact I can't do anything before or after (without being out till silly hours)
 
This may sound a daft question, but how would you carry out the install?
By that I mean will you be chasing all cables in, or will you be running surface mounted behind units, cupboards etc?

Edit
Forget that question, I've read the original post properly now, doh!
 
Last edited by a moderator:
i think you're bang on. if anything you're on the low side. the guy's a cheapskate, trying to screw the price down.
 
Don't doubt yourself Sparx, your price is exactly how you saw it and if customer thinks otherwise then it is him who has the prooblem andhe is just not appreciating that you are pricing it around odd starting times. You have a two days to account for, bang on as I see it.
 
Sounds good to me as well. I usually find that with kitchens you never just go twice, once for 1st fix, and once for 2nd. Something always changes, or gets cocked up by fitters or plumbers and you can end up going backwards and forwards forever and a day. So tell your client this, and give him the choice, you can go back 2 or 3 times extra if required in with the price, or you can knock a bit of the quote and you will charge him your hourly rate for each and every extra visit over the 2 quoted for. Anyway your price looks good, so tell him to take it or leave it.

Cheers...........Howard
 
2 days is about right BluSparx, I would probably of added 1/2 a day for being messed around as Howard says and for the post job paperwork.

3 hours to second fix is too tight (who quotes for 3 hours work anyway, it has to be 1/2 a day) 6 sockets, 1 cooker point with 2 appliances, 5 down lights & then them pesky under unit lights. They would take me almost 3 hours alone nowadays with my eyesight and all that bending over and working upside down.

Then not forgetting testing & certification.

As a side point, I try not to break down my quotes into time & materials as this can lead to the client asking for a reduction if you manage to finish a job a day early but you can be sure that there will be nothing extra if the job over runs by a day.
 