Just a quick price check

Client is having the wall between kitchen and dining room taken out to make 1 big kitchen, about 20 mins from where I live.
Replace CU, upgrade meter tails and all earthing and bonding, also need to chase out wall and ceiling to run bonding to water (can't go round).
13 spotlights with 2 way switching at both ends of the kitchen, moving cooker cable and sockets and he wants the 3 gang sockets.
Gonna get a mate to help with first fix, have allowed 2 days for first fix, 2 days for finishing and a day for the CU..

I reckon about £1800.

Thanks.
 
Last edited:
CU and bonding = 550
lights = 715
switch drops = 150
extra sockets = 250 (based it on 4-5 alterations)

total £1665***** purely based on what you have said..!
 