L

Luke105

Evening all.

Is there a stigma of signing off someone else’s work?
If you came out and tested and all was ok…are you happy to sign off?

Anyone who strictly would not entertain this?

I don’t have the test and inspect certs so am unable to do this but don’t want to run into a problem once I’m ready for sign off.

Just like peoples opinions.

Thanks
 
no,you will be liable for it .but do a EICR before hand and everything fine then it your call.
Sorry. Before what?

I’ll just explain the situation.

We need to do a rewire in a house we are buying. We aren’t able to pay for a rewire as the costs are just too high.

I would like to do the rewire. I’m able to leave plaster off, ceilings down so wires can be seen.

If I was to do this and get an EICR would this be ok?

Feel like I’m stuck in the mud.
 
I think I need to do some investigating on the notification before things start.

I’ve done part p and 18th edition wiring regs but haven’t done my testing so those 2 quals I do have seem pretty useless.

Let me put a scenario to you…..If I was to rewire everything socket and switch wise….feed everything into a board so it works.

Could I not get an electrician round to simply install a new board?

That way it’s in essence just a board change and they should be happy I sign it off once new board is fitted.
 
Only you would do that buzz.. 😂I dont know any who would give up their time for him to save cash, again unless they know him
 
speak to the local building control
if you notify them before the work starts and submit the correct certificates they should allow it, there is often a charge for the service.
 
Could I not get an electrician round to simply install a new board?

That way it’s in essence just a board change and they should be happy I sign it off once new board is fitted.
What you appear to be missing is that the replacement of the DB would literally be the ONLY thing they were certifying. They would not be certifying any existing work whatsoever.
 
What you appear to be missing is that the replacement of the DB would literally be the ONLY thing they were certifying. They would not be certifying any existing work whatsoever.
No they wouldn’t. But they would test the board and circuits and sign off. If everything tested ok then that sounds ok? Or is it still dodgy.

I can’t see this causing me any issues now or further down the line? What do you think
 
speak to the local building control
if you notify them before the work starts and submit the correct certificates they should allow it, there is often a charge for the service.
I did look at this and maybe I should call them.

Is it a case of notifying them and paying a fee.

Do first fix, they come and check. Do second fix they come and sign off?

Do I need a certified electrician to sign the job or test etc?
 
Don't even think about a 'board only' test, all the work needs to be certified.

speak to the local building control
if you notify them before the work starts and submit the correct certificates they should allow it, there is often a charge for the service.
That's the way to go if you have no qualified person to help.
Someone may help you out for less cost than the first option. Get a price from Building Control.
 