Hello all, I recently was asked to quote a three phase motor install within a pallet factory. To be honest, I was somewhat stumped in how to attack it as the sheer size and the control cabinet was gigantic. Although I'm mainly a domestic, commercial spark, this was somewhat out of my league. The motor was rated at 90kw, three phase, pf was 0.85, so current would of been around 150 amp per phase. The supply coming in was a 200amp, possibly 250 ( I don't remember exactly) and a standard three phase consumer unit. The control unit had an array of contactors and overloads, now I'm ok with motors and starters to a certain degree, ie forward reverse, on delay off delay, start delta, but this was out of my league. My questions are as follows as..
Would this require a separate circuit with a large type three phase isolator just for the motor? IE fed from a bussbar chamber.
Who would I need to speak to, IE in this regard as most sparks would struggle including myself, thank you in advance
 
Usually the machine manufacturer has done most of the work for you, on the machine nameplate or instructions will be the machine power requirements.

I.E. 400v 3ph 200A

solve it the same way you would approach any new circuit, calculate your cable size and ensure the isolator is able to accept both the current and the size of cable required.

as for a suitable breaker, some distribution boards allow for breakers in the 200A range, check with the manufacturor of the board.

if not, often a fused isolator is the easiest way to go and yes if there is a bus bar chamber feeding the boards then that may well be a suitable place to take the supply from.
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread starter

Joined
Location
Birmingham
Business Name
Electrical solutions

Thread Information

Title
Three phase motor help
Prefix
N/A
Forum
Talk Electrician Forum
Start date
Last reply date
Replies
3

Advert

Thread statistics

Created
Zahid Nawab,
Last reply from
netblindpaul,
Replies
3
Views
1,843

Advert

Back
Top