Just a quick one for you..
I have been asked on the phone to come and install a new feed to a porta cabin & test once complete,
A tempory armoured feed will run from existing building and hook up to the CU in the cabin, I think im right in saying i need to TT the cabin if water services and extrenous parts within.?
Also when it comes to testing, I will test the armoured feed installed to the cabin, which will be an EIC. will i need to PIR the cabin it self ?? or not test anything within the cabin?