BluSparx

3 bed rewire, no problems i'll do it in 5 days - unoccupied me and employee

day 1 - send in the labourer to chase

day 2 - first fix backboxes & downstairs cables, hold on we hit a problem the walls are not thick enough to even put a 25mm double backbox in upstairs and the customer ain't best pleased as the boxes stick out a little - explained to customer the situation and that he is going to need to reskim after completion as in some places the plaster is around half an inch thick in other no thicker than 2mm

ok over the worse ........ or so thought turn up day 3 water dripping down from the screwhole of the battery operated smoke took down yesterday. - turns out the seal has gone on the water header tank ..... oh well at least I can't get blamed

day 3 waiting for plumber no show empty the water tank for customer and turn off outside supply ---- 4 hours later now lets get on with the wiring.

day 4 ----- wiring in sockets attached, light fittings next - mr customer stood over me and then says you have pride in your work however can i move this switch aaaaaaaaaaaaaahhhhhhhhhhhhhhh

day 5 ----- cu to install goes without a problem

next left to test and hopefully only 1 day over last day tomorrow

onwards and upwards eh
 
probably the 2" thick breeze blocks councils used to love.
 
they the ones literally are 2" thick breeze block ridiculous stuff even charcoal is stronger
 
what i try to do with those walls is get the client to agree sockets back to back if prfacticable. then bolt 2 knockout boxes together and stick em in with one-coat. also does away with 1 chase.
 