S

shagg

How much would you guys charge for a PIR on a ciema :confused:. It's got 37 circuits in all split over 5 Consumer units. It looks like a pretty strainght forward job but in my book they tend to be the worst :rolleyes:. I'm hoping to pick up his pat testing work as well all being well.

P.S. there's no limitations
 
Last edited by a moderator:
No limitations......is it a small cinema then, or are we talking UCI size???

Removal of lamps etc could be a headache with the high ceilings etc. What about sampling, are you saying it's 100% of accessories inspected??
 
I can't tell you what to charge, what's your hourly chargeable labour rate?

Then look at per-circuit times, normally around 0.5 hours per circuit.

Have you agreed a percentage for detailed inspection?
 
No limitations......is it a small cinema then, or are we talking UCI size???

Removal of lamps etc could be a headache with the high ceilings etc. What about sampling, are you saying it's 100% of accessories inspected??

sorry it will be sampling and its only a local cinema so not on the same scale as UCI.

I can't tell you what to charge, what's your hourly chargeable labour rate?

Then look at per-circuit times, normally around 0.5 hours per circuit.

Have you agreed a percentage for detailed inspection?


I havn't agreed a percentage yet, I need to discuss that with him latter tonight. I was thinking between £15 to £20 a circuit.
 
If the PIR is part of Local Authority requirements, percentages may already be given along with requirements for fire alarm interfaces to bring onlighting and cut sound in alarm conditions.

Not part of a PIR but you might be asked to confirm operation of these special requirements.
 
It's difficult to balance.....new customer and you're looking for more & repeat work so dont want to go in heavy.

Have you seen the job at all yet....any previous reports, is everything labelled up etc??
 
Seen the job today everythings labled so that's not to much of a problem. The lad who meet me didn't know anything about former cert though, so need to Chase the owner. Cheers for the heads up about the sound system.
 
Any odds and sods need to be taken into account before you quote for the PIR. They should be listed in the EXTENT part of the report in my opinion. Something like "full fixed wiring installation. and including blah blah blah". this way you and they cover arses, and there is no disagreement at a later date, like on payday!

Cheers...........Howard
 
Following the demise of cellulose nitrate film and limelight illumination the act was suspended.
 