Morning Chaps...
Have only wired a couple of conservatories previously so after some advice as this one isnt being constructed as expected.
Off to first fix later this afternoon ...... builder is compacting a layer of hardcore then tomorrow will be cellotexing and laying a concrete screed on top, no block work up yet, he's laying first course today.
So I've got to get my cables all around and in place before the celotex/ concrete goes down.
I was under the impression 'from customer' that a concrete base was being laid first, cellotex on top of this then final screed - but not so. If this was the case simple copex/conduit around the edge fixing in place to concrete base/ blockwork with loops sticking up ready.
Now not too sure what I'm suppose to fix to... got a hardcore base and green walls ? Only option is looking like conduit just floating in place hoping the builders dont wreck it ?
Help any suggestions please?
Many Thanks,
Sy
Have only wired a couple of conservatories previously so after some advice as this one isnt being constructed as expected.
Off to first fix later this afternoon ...... builder is compacting a layer of hardcore then tomorrow will be cellotexing and laying a concrete screed on top, no block work up yet, he's laying first course today.
So I've got to get my cables all around and in place before the celotex/ concrete goes down.
I was under the impression 'from customer' that a concrete base was being laid first, cellotex on top of this then final screed - but not so. If this was the case simple copex/conduit around the edge fixing in place to concrete base/ blockwork with loops sticking up ready.
Now not too sure what I'm suppose to fix to... got a hardcore base and green walls ? Only option is looking like conduit just floating in place hoping the builders dont wreck it ?
Help any suggestions please?
Many Thanks,
Sy