sythai

~
Arms
Morning Chaps...

Have only wired a couple of conservatories previously so after some advice as this one isnt being constructed as expected.

Off to first fix later this afternoon ...... builder is compacting a layer of hardcore then tomorrow will be cellotexing and laying a concrete screed on top, no block work up yet, he's laying first course today.

So I've got to get my cables all around and in place before the celotex/ concrete goes down.

I was under the impression 'from customer' that a concrete base was being laid first, cellotex on top of this then final screed - but not so. If this was the case simple copex/conduit around the edge fixing in place to concrete base/ blockwork with loops sticking up ready.

Now not too sure what I'm suppose to fix to... got a hardcore base and green walls ? Only option is looking like conduit just floating in place hoping the builders dont wreck it ?

Help any suggestions please?

Many Thanks,

Sy
 
Have the afternoon off...........................Wait until the block work is up.
I've only ever put conduit round the floor on conservatories twice usually:
  • clip direct round walls before dot dab/plaster.
  • Get conservatory fitters to put over width window boards in, then run trunk surface under the bull nose (only if already plastered as it looks ****e)
  • If raised wood floor on top of screed, clip to the screed & make a service duct where no insulation is placed under floor.
 
Last edited by a moderator:
Tiles straight on top of screed.... only prob is the wall isnt continuous all the way around, 4 openings for doors.

Looking at it again I suppose I could copex in between door ways and just bury in the hardcore, then clip along the walls.

Panic over:6:
 

OFFICIAL SPONSORS