Been having a bad run of luck recently because the last 3 CCU's I've updated have all been riddled with faults.

Went to do one last week but decided to decline doing it there and then! The house was in a row of semi's built in 1971/2. The house was fitted with an 8way Wylex 3036 board and everything looked original, so I was thinking it shouldn't take too long.

Turns out there's two circuits (ring & radial skts), with neutral/earth faults, then I find the real sh1tter. The ring and immersion circuits have been wired in old rubber cable - RUBBER CABLE & BUILT IN THE SEVENTIES!!!!!!!! I can imagine that spark saying - "Think I'd better use this old crap up, while I still can"

I wonder how these Super Sparks who complete 2 CCU updates every day, would manage this one???
 
They would cut the last foot off each rubber circuit and choccy a bit of t&e on the end then stick the floorboard back down!
 
I always allow 1 day for a CU change. Maybe the people that claim to do 2 per day, are doing 4 circuit houses and skimp on the testing.
 