Wilko
Hi All, I'm working on an older agricultural installation (100A single phase) and would appreciate your thoughts on earthing details 
Main building is TT. Well it is now that I've installed some rods and reinstated it... There is an outbuilding with some pumps etc that I'm also upgrading. It's about 50m away, supplied by SWA from the main building with armour as CPC. I plan to rod the outbuilding and am thinking to combine the 2 earth rod installations by continuing the SWA armour into the sub board in the outbuilding. My thought being to reduce the installation's Ra and improve its resilience. Or should the 2 buildings means of earthing be kept separate?

Main building is TT. Well it is now that I've installed some rods and reinstated it... There is an outbuilding with some pumps etc that I'm also upgrading. It's about 50m away, supplied by SWA from the main building with armour as CPC. I plan to rod the outbuilding and am thinking to combine the 2 earth rod installations by continuing the SWA armour into the sub board in the outbuilding. My thought being to reduce the installation's Ra and improve its resilience. Or should the 2 buildings means of earthing be kept separate?