Leesparkykent
Nice sized job. What is it new build, refurb etc?
only if they spec that they want rcbos- if not just fit a dual rcd boardits a new build, not sure if i have the minerals to take it on as ive never priced something like this. would you fit rcbos on a job this big Lee?
its a new build, not sure if i have the minerals to take it on as ive never priced something like this. would you fit rcbos on a job this big Lee?
make sure your terms and conditions are water tight and provide a spec on what your price is based on. Get the customer or builder to sign for any extras as they go in and provide the price before you install them as that's where many get stung at the end.I wouldn't worry about it mate. Price it accordingly leaving a little margin for error, there isn't much that can go wrong as long as your competent. My main game is high end new build, If you put up a detatiled list of whats going in I would tell you my price and I haven't lost out yetmake sure your terms and conditions are water tight and provide a spec on what your price is based on. Get the customer or builder to sign for any extras as they go in and provide the price before you install them as that's where many get stung at the end.
Good advice thanks Lee ! how much labour would you throw at this ? 2 sparks and a mate ? probably looking at 2 weeks for 1st fix
Without looking at a break down its hard to say. Its always good to have another sparks you trust to bounce ideas off and to help with the main bulk of the 1st fix on jobs this size as takes a lot of pressure off yourself and an apprentice/mate to do the donkey work like capping, fetching and carrying. Your going to have to break the job down in to four stages.1st fix, mid fix, second fix and snagging/testing. Having 200 + downlights to cut out during the mid fix after its been plastered but before its been painted is a task on its own. I wouldn't want to loose the drawings marking out the down lights lol. Its a good job my apprentice is skinny as I cant fit my hand in to a 75mm hole but he can past his elbow so he makes light work of fishing the down light cables out.
Without looking at a break down its hard to say. Its always good to have another sparks you trust to bounce ideas off and to help with the main bulk of the 1st fix on jobs this size as takes a lot of pressure off yourself and an apprentice/mate to do the donkey work like capping, fetching and carrying. Your going to have to break the job down in to four stages.1st fix, mid fix, second fix and snagging/testing. Having 200 + downlights to cut out during the mid fix after its been plastered but before its been painted is a task on its own. I wouldn't want to loose the drawings marking out the down lights lol. Its a good job my apprentice is skinny as I cant fit my hand in to a 75mm hole but he can past his elbow so he makes light work of fishing the down light cables out.
Got a good guy I think is going to work along side me if I get it.

Hi mate I had a look through drawings and made a quick total of the different items and come to a price of around 27K-28K. There is a hell of a lot of gear going in![]()
i did a quick gestimate the other day and got 30k, ill post some more information up when i get it,cheers

Happy days. I've just been given the drawings for 14 new build 4 bed detached houses today that are supposed to be ready early next year![]()
Yeah no probs, ill scan them in at the office 2moz and put them up. The builder who they are for is a good friend, he's actually the person who funded everything for me when I 1st set up properly about 8 years ago. Brand new van, tools, NIC registration etc and funded me wages until it all took off as had two babies at home. managed to pay him back within a year out the work he put my way lol. He tells me what he has allowed and asks if I can do it for it...He roughly averages it out at £45 a point.Nice one Lee, can you stick something on here at some point so we can have a go at pricing it ? Hope you get the job.