Live testing of MV/HV equipment is normally kept to a minimum. Most testing of these systems are ''dead tests'', on rare occasions as Tony stated you may need to conduct phasing or to confirm live test with probe sticks. Most of the testing to energised systems, come in the form of proving an area which is to be worked on has been de-energised by isolation and the cable cores earthed!! Testing can be just as perilous even on some of the dead testing, such as the Hi Pot tests, which are often conducted at more than twice the nominal voltage...lol!!
Is it dangerous, of course it is, if you don't know what your doing or get careless!! MV/HV systems always command a great deal of respect... One thing you always remember, you don't need to touch these voltages levels, they come out to grab you when you get too close, the higher the voltage the greater the distance it can jump to grab you ...lol!!
Like Tony, I had a lot of intensive training and experience on these distribution systems, from my apprentice days right the way through to the present day. My ''Authorised Person'' training was with both as was then Eastern Electricity Board and the London Electricity Board but i was much younger than Tony at the time. Unlike Tony, i didn't attend jointing training, but have on more than the odd occasion helped certified jointer's, on dead direct buried joints...
Can't tell you how much any of this training costs these days as i have never paid, it's always been company provided. As far as i know, (but it may have changed) You don't need the ''Authorised Person'' status to work on MV/HV, you can also get ''Certified Person'' status, who works under the supervision and control of an Authorised Person...